The Department of Planning & Project Management has announced an abundance of summer improvement work on the River Campus. Thirteen projects are planned through September, including completion of the renovation of the athletic center, restorations to Rush Rhees Library, and the addition to Schlegel Hall, which will continue into next year. For more information call Paul Tankel, x5-0936, or e-mail paul@facilities.rochester.edu.
| 1 | FAUVER STADIUM TRACK AND FIELD REPLACEMENT (May through August) |
| 2 | SPURRIER HALL RENOVATIONS (May through August)
Dance studio and infrastructure |
| 3 | MORGAN HALL ROOF REPLACEMENT (July through August) |
| 4 | DANDELION SQUARE (March through August)
Landscaping and site amenities |
| 5 | ATHLETIC CENTER (March through August)
Phase Two of renovations |
| 6 | WILSON COMMONS/MOREY HALL (May through August)
Renovations for Dean of Students Office/Office of Minority Student Affairs |
| 7 | RUSH RHEES LIBRARY TOWER RESTORATION (May through August) |
| 8 | RUSH RHEES LIBRARY GREAT HALL RESTORATION (June through September) |
| 9 | MELIORA PLAZA (May through August)
Waterproofing and paving |
| 10 | HOYT HALL ROOF REPAIRS (May through June) |
| 11 | SCHLEGEL HALL ADDITION (May through August 2001) |
| 12 | FRATERNITY QUAD SIDEWALK AND LIGHTING (May through August) |
| 13 | WILLIAMS COMMUNICATIONS (June through August)
Underground conduit easement |
| | CAMPUSWIDE (June through August)
ADA improvements |
| | CAMPUSWIDE (May through August)
Paint and carpet replacement |