Procure to Pay Transformation two year schedule
- Jan – Oct 2018 Procurement, AP Readiness, IT Design and Configure, Training Build, Test
- June 11 2018, First Go Live, Early User Acceptance Test Workday only,
- Nov – Dec 2018 Workday/ Jagger Sandwich model User Acceptance Test
- June – Dec 2018, continued Procurement and AP readiness, Training, IT Design and Configure Sandwich Model.
- Feb – April 2019 2 pilots, test solution, training material and communications
- July 2019 – February 2020 Roll out in 4 phases